Minneapolis spent most of 2026 trying to write rules for data centers, the warehouse-like buildings full of computer servers that power the internet, and on Friday, November 20, the effort stalled at the final hurdle. The Minneapolis City Council voted 7-5 to override Mayor Jacob Frey’s veto of a data center ordinance it had passed the week before, falling two votes short of the nine needed to overturn a mayoral veto. The result left the city without the new regulations on the very weekend its six-month moratorium on new data center development expired, and it sent the issue back to the start of the city’s review process, with a new public hearing planned for December 14 and a council vote expected on December 17.
The vote was the end of a long and often tense debate at City Hall, one that pitted council members who wanted strict limits on where data centers could go against a mayor who said the council’s final version would amount to a ban in all but name. Both sides said they wanted rules. Both sides said the industry needed regulation. But they disagreed on a single provision added at the last minute, a requirement that the council approve each new data center individually, and that disagreement proved impossible to bridge before the moratorium ran out on Saturday, November 21.
The failure mattered beyond the council chamber. Data centers use large amounts of electricity and water, they can generate noise from cooling equipment and backup generators, and they occupy buildings that might otherwise hold offices, shops or homes. In a city where downtown office space is plentiful and the tax base is under pressure, the question of whether to welcome data centers, restrict them or keep them out altogether has become a test of how Minneapolis wants to grow. The council’s vote did not answer that question. It postponed it, by about a month, and left the city to operate in the meantime under its old zoning rules.
Friday’s meeting also dealt with a second veto, over the mayor’s nominee for police chief, and the council failed to override that veto by the same 7-5 margin. The two votes together made November 20 one of the most consequential days of the year at Minneapolis City Hall, and they showed a council and a mayor who, for all their agreement that data centers and police leadership need attention, could not muster the supermajority required to impose their will over the mayor’s objections.
Minneapolis Data Center Veto Override Falls Two Votes Short
The Minneapolis City Council met on Friday, November 20, to consider two vetoes issued by Mayor Jacob Frey the day before. The first concerned the data center ordinance. The council had approved the ordinance on November 12 by a vote of 7-6, a narrow margin that already fell short of the nine votes needed to override a veto. Frey vetoed it on Thursday, November 19. When the council took up the override on Friday, the vote was 7-5, with Council Member Jamison Whiting absent. Seven votes were not enough. Nine were required, and the veto stood.
The numbers tell the story of the whole dispute. The ordinance passed with seven votes. The override attempt drew the same seven votes. The council could not add the two extra votes it needed, and the mayor’s veto survived. Council Vice President Jamal Osman, who represents Ward 6, was among those who voted to override. He had opposed the final version of the ordinance the week before, warning that the last-minute additions could prevent the package from becoming law before the moratorium expired. On Friday, he voted to override the veto anyway, saying the city needed the protections the ordinance contained, even in a form he had not fully supported.
Seven of us voted to override, Osman wrote in a statement to residents after the meeting. We needed nine. His account captured the arithmetic that decided the issue: a majority of the council wanted the ordinance to become law, but a majority was not enough. Under the city’s rules, overriding a mayoral veto requires nine votes, a supermajority designed to make vetoes hard to overturn, and the council could not reach it.
The vote also reflected a division that had been visible for months. Council members who supported the ordinance argued that data centers needed firm limits on location, size and resource use before any new projects were approved. The mayor and his supporters argued that the final version went too far, and that the requirement for individual council approval of each project would discourage investment in a downtown that needs it. Neither side changed the other’s mind on Friday, and the vote ended the same way the original vote had, with seven in favour and the rest opposed or absent.
What the Vetoed Data Center Ordinance Would Have Required
The ordinance the council passed on November 12 was the product of about six months of work by city staff and council staff, who had spent the year developing a regulatory framework while a temporary moratorium paused most new data center proposals. The framework that emerged set limits on where data centers could operate, how large they could be and what their operators would have to disclose about their use of electricity and water.
Under the vetoed ordinance, new data centers would have been allowed only inside existing buildings, and only in two downtown zoning districts. A data center could not be the primary use of a building, and servers could not be placed on the first or second floors. The idea, as council supporters described it, was to keep data centers from taking over street-level space that could hold shops, restaurants or other businesses that bring people downtown, and to confine them to parts of buildings where their impact on the street would be limited.
The ordinance would also have required operators to disclose how much energy, water and generator capacity they expected to use, to prepare a sound attenuation plan to limit noise, and to prepare a plan for decommissioning a facility that stopped operating or went out of business. Facilities larger than 50,000 square feet would have had to enter a programme with Xcel Energy in which owners pay a premium to support renewable energy through the purchase of renewable energy credits. The maximum computing area, known as white space, was set at 150,000 square feet under an amendment brought by Osman and Council Member Michael Rainville, down from 175,000 square feet in an earlier draft.
The provision that proved decisive was added late in the process. A majority of the council added a requirement for an overlay district at each proposed data center site, which in practice would have meant a separate council rezoning decision for every new project. Supporters said the requirement would give the council and the public a say over each proposal. The mayor said it would give the council a veto over every project, and that the cumulative effect would be to stop new data centers from being built in Minneapolis at all.
The council also considered a full ban on data centers, and that proposal failed to pass. The ordinance that reached the mayor’s desk was therefore a compromise, stricter than the framework city staff had originally presented but short of an outright ban. It was that compromise, with the overlay requirement attached, that Frey vetoed.
Why Mayor Frey Vetoed the Data Center Rules
Mayor Frey did not reject the idea of regulating data centers. In his veto letter, he wrote that he would sign the framework city staff had originally presented, which he described as one of the strictest data center regulatory frameworks in the country. His objection was to the changes the council made to that framework, and in particular to the requirement that each new data center receive individual council approval through an overlay district.
Frey said the last-minute changes would result in a de facto ban on data centers in the city. He objected to the council’s proposed changes to primary zoning and to the requirement for an overlay district at each proposed site. He also argued that a strong commercial tax base was needed to support the robust social programmes that serve the city’s residents, a point that framed the dispute as a choice between regulation and revenue. Data centers, in the mayor’s argument, would pay taxes on buildings that might otherwise sit empty, and turning them away would weaken the city’s ability to fund the services its residents rely on.
The mayor’s position also drew support from parts of the city’s business community, which argued that the restrictions would discourage investment downtown. Council members who opposed the ordinance made a similar argument, saying that vacant office space needed new uses and that data centers, whatever their drawbacks, would bring investment and tax revenue to a downtown still recovering from the loss of office workers.
Osman, in his statement after the vote, acknowledged that the mayor had made clear he would veto the approach the council adopted. He said he had warned his colleagues that without the votes to override the mayor, the additions could prevent the entire package from becoming law before the moratorium expired. That is why I opposed the final version last week, he wrote. The warning proved accurate. The council added the provisions the mayor had said he would veto, the mayor vetoed them, and the council could not override him.
The Moratorium Expires on November 21
The timing of the vote gave the failure an immediate consequence. The city’s six-month moratorium on new data center development, a temporary pause approved earlier in 2026 while the city created new standards, was set to expire on Saturday, November 21, the day after the council’s vote. With the ordinance blocked, the moratorium lapsed with no replacement rules in place.
As the moratorium expires, Minneapolis will not have regulations on data center size, noise, energy or water usage, according to reporting by KSTP, the local television station. Council members and the mayor had both wanted guardrails, according to Council Member Michael Rainville, but the city now has none of the specific protections it spent months developing. Data centers will be able to seek permits under the existing zoning framework, which allows them in 10 of the city’s 15 primary zoning districts, Osman wrote.
The practical effect is narrower than it might sound. The city told KSTP that there are no data center applications in place right now, so no project is waiting to take advantage of the gap. The moratorium had also never applied to downtown projects smaller than 350,000 square feet, according to MPR News reporting, which means part of the downtown market was never paused at all. The lapse is therefore a window rather than a floodgate, a period of about three weeks in which the old rules apply while the council works on a replacement.
That window matters all the same. A developer could, in principle, submit an application under the old zoning rules before new regulations take effect, and the city would have to consider it under the framework that existed before the moratorium. Council members who supported the ordinance warned of exactly that risk, saying the city had lost the protections it had spent six months developing. The mayor’s supporters countered that the risk was theoretical, since no applications were pending, and that the council would have new rules in place by December 17.
The Police Chief Veto and the Same 7-5 Split
The data center vote was not the only veto the council considered on Friday. Frey had also vetoed the council’s rejection of his nominee for police chief, Interim Chief Bill Peterson, and the council’s attempt to override that veto failed by the same 7-5 margin, also falling two votes short of the nine needed.
Peterson took the role of interim chief after the resignation of Brian O’Hara in May 2026. The council denied his confirmation in an 8-5 vote the previous week, and the mayor vetoed that rejection, hoping to secure the simple majority needed to confirm Peterson for the permanent role. The council’s failure to override the veto means the nomination process starts from the beginning if the mayor chooses to re-nominate Peterson, according to FOX 9 reporting.
Osman voted to sustain the mayor’s veto on the police chief nomination, the opposite of his vote on data centers. He wrote that he had voted to confirm Peterson with certain expectations and would continue to judge the chief’s leadership by whether he delivered on them. He also said he had moved to refer the nomination to the City Clerk so the council could revisit the appointment, a motion a majority of his colleagues supported. Peterson continues to serve as interim chief, and his permanent appointment remains pending.
The two vetoes together showed the limits of the council’s power when it cannot muster nine votes. On both issues, seven council members wanted to overrule the mayor. On both issues, seven was not enough. The result left the mayor’s decisions in place on both the data center ordinance and the police chief nomination, and it left the council to find another path forward on each.
The Compromise Path: December 14 and December 17
The council did not end Friday’s meeting empty-handed. In the afternoon, it unanimously agreed to send the earlier compromise framework back to the Planning Commission, the body that reviews zoning changes before they reach the council. A public hearing is planned for December 14, with council action expected on December 17. City attorneys told the council that December 17 was the earliest date on which new regulations could be adopted, according to KSTP.
The compromise framework is the version city staff originally presented, the one the mayor said he would sign. It contains limits on location and size, requirements for operators to disclose their resource use, renewable-energy purchasing requirements and public review, according to Osman’s account of the six months of work that produced it. What it does not contain, in its original form, is the overlay requirement that the mayor said would amount to a ban. The question for December is whether the council can agree on a version of the framework that keeps the protections its members want without adding the provisions the mayor has said he will veto.
Council Member Soren Stevenson said the council planned to return to the issue quickly. The December timetable gives the council about a month to negotiate, hold a public hearing and vote, and it gives the mayor a chance to sign a framework he has already praised. Whether the two sides can reach that agreement will depend on whether council members who wanted the overlay requirement are willing to accept a version without it, and whether the mayor is willing to accept the rest of the package.
The December dates also set a deadline for the public. Residents, business owners and data center operators will have a chance to comment at the Planning Commission hearing on December 14, and the council’s vote on December 17 will be the next decisive moment. If the council passes a compromise and the mayor signs it, Minneapolis will have data center rules before the end of the year. If the council cannot agree, or if the mayor vetoes again, the city will enter 2027 still operating under its old zoning rules.
What Minneapolis Residents Told the Council
The debate over data centers drew intense public interest. According to an MPR News analysis of the public comments submitted to the city, about 1,600 written comments were received on the rules, and almost half of them asked for an outright ban on data centers. The figure shows how strongly some residents felt about the issue, and how far the council’s compromise fell short of what the most vocal opponents wanted.
The concerns behind those comments were familiar from data center debates in other cities. Residents worried about the amount of electricity the facilities would use, about the water needed for cooling, about noise from cooling equipment and backup generators, and about the effect of large, windowless buildings on neighbourhoods. Some argued that data centers create few permanent jobs relative to their size, and that the buildings they occupy could be better used for housing, offices or shops. Others worried that the facilities would strain the electricity grid and raise costs for other customers.
Supporters of allowing data centers made a different case. They argued that vacant downtown buildings needed new tenants, that construction of the facilities would bring work for building trades, and that data centers would pay taxes that help fund city services, even though the buildings employ relatively few people once they are running. The debate, in other words, was not between people who cared about the city and people who did not, but between two different ideas of what the city needed most: protection from the side effects of data centers, or investment in buildings that would otherwise sit empty.
The council’s vote did not settle that argument. It showed that the public was divided, that the council was divided, and that the mayor and the council disagreed on how far regulation should go. The December process will give residents another chance to be heard, and the comments submitted then will be part of the record the council considers when it votes.
What to Watch Next in Minneapolis
The next month will decide whether Minneapolis gets data center rules this year. The Planning Commission hearing on December 14 is the first public test of the compromise framework, and the council vote on December 17 is the decision point. The key question is whether the council can find nine votes for a version the mayor will sign, or whether the mayor will accept a version that keeps some of the provisions he objected to.
Several things are worth watching as that process unfolds. The first is whether the overlay requirement returns in any form. It was the provision that caused the veto, and its fate will tell observers whether the council has learned the lesson of November 20, that a package the mayor has said he will veto needs nine votes to survive, and the council does not have them. The second is the size limit. The council reduced the maximum computing area from 175,000 to 150,000 square feet in its final version, and the figure that emerges in December will show how restrictive the final rules are intended to be.
The third is whether any developer files an application while the old rules are in effect. The city says none is pending, but the gap between the moratorium’s expiry and the adoption of new rules is an invitation, and an application filed in that window could test the city’s willingness to approve a project under the old framework. The fourth is the police chief nomination, which remains unresolved alongside the data center question and will return to the council in its own time.
For now, Minneapolis is a city that tried to write rules for a new industry and ran out of time and votes. The moratorium has expired, the ordinance is dead, and the old zoning rules apply. The work that went into the framework has not been wasted, because the compromise version is already on its way back through the review process. But the lesson of November 20 is clear: in Minneapolis, a regulation that the mayor opposes needs nine votes to become law, and the council, for all its months of work, could only find seven.
Sources